1. Prepare the Site
Single Steam Head Installations
IMPORTANT! The steam head must be installed at least 6 (15.2 cm) from the floor in an area where
contact with occupants is unlikely.
IMPORTANT! Provide clearance between the back wall and the elbow. The elbow should not contact the
back wall.
NOTE: The edge of the hole should be at least 1 (2.5 cm) away from all wall studs.
Drill a 2-1/2 (6.4 cm) diameter hole in the wall at the desired steam head location.
NOTE: For all the connections, use thread sealant tape and do not overtighten the fittings.
Install a 1/2 NPT connection on the end of the steam housing assembly.
Secure the connection to the framing whenever possible.
NOTE: The steam generator(s) will not operate without water and a connected user interface control.
6" (15.2 cm) from Floor
4-1/2" (11.4 cm)
Min
Provide clearance
from wall.
Wall Stud
2-1/2" (6.4 cm)
1" (2.5 cm) Min
Custom Shower
Applications
1045320-2-D 6 Kohler Co.